A superload permit is a state permit for a move that goes past what the state’s routine oversize or overweight permit allows. No federal rule sets that line. FHWA’s permit page says “The Federal government does not issue permits for oversize or overweight vehicles” and calls permits “a State option.” An FHWA best-practices report on OS/OW permitting adds that “State permitting practices vary significantly.” So the same load can be routine in one state and a superload in the next.

The superload glossary entry covers the term. Here is where six states draw the line and what changes once you cross it.

Thresholds side by side

A load is a superload in these states if it crosses any one of the listed limits.

StateWidthHeightLengthGross weight
PennsylvaniaOver 16 ftNot in the definitionOver 160 ftOver 201,000 lbs
North Carolina17 ft or moreNot in the definitionNot in the definitionOver 132,000 lbs
OhioNot in the definitionNot in the definitionNot in the definition120,000 lbs or more
IndianaOver 16 ftOver 15 ftOver 110 ftOver 120,000 lbs
Delaware15 ft or more15 ft or more120 ft or more120,000 lbs or more
VirginiaCase by caseCase by caseCase by caseCase by case

A 200,000-pound move is a superload in Ohio, Indiana, Delaware and North Carolina, and still under Pennsylvania’s weight line. This table covers six states. It is not a 50-state list, so check every state on your route.

Pennsylvania

67 Pa. Code § 179.1 defines a super load as “A vehicle or combination or load having a gross weight exceeding 201,000 pounds, a total length exceeding 160 feet, or a total width exceeding 16 feet.” Three moves are excluded: a building moved under § 179.11(b), a highway crossing under sections 4965 or 4966 of the Vehicle Code, and a dragline moved across the highway.

What changes for a super load:

  • Police escort. Section 179.10(12) requires “An escort by uniformed State Police or local police” for super loads. When the State Police must escort, PennDOT needs the application in time to notify them at least 24 hours before the move starts.
  • Paperwork. PennDOT’s APRAS FAQ says all super load applications need Form M-936MDC (Manufacturer/Designer Certification) and Form M-936ARS (Route Survey).

North Carolina

NCDOT’s Superload Publication SL-6 lists weight “greater than 132,000lbs.” and width “17’ or greater.” For a superload, SL-6 sets these terms:

  • Apply at least 10 business days before the move, so the office can finish internal and bridge engineering reviews.
  • The permit is valid for 10 days for one single trip. A return trip needs its own application.
  • A $100 nonrefundable application fee, a $12 base fee for each over-legal dimension, and $3.00 per 1,000 lbs over 132,000 lbs.
  • Travel runs sunrise to sunset, Monday through Sunday, unless the permit says otherwise. Continuous travel is not authorized.
  • Loads over 16 feet wide need three escorts, and one must be the NC State Highway Patrol.

SL-6 also says bridge engineering studies expire after 90 days, and the application is then void. The superload vs oversize load entry covers the gap between NCDOT’s handbook (over 16 feet) and SL-6 (17 feet or more).

Ohio

ODOT’s Bridge Management FAQ is one sentence long: “In Ohio, a Superload is any highway vehicular load with the total gross load equal to or more than 120,000 pounds.” The page does not list a width, height or length trigger. Ask ODOT’s permit office what an oversize-only move needs.

Indiana

The Indiana Department of Revenue issues the state’s OS/OW permits. Its FAQ says: “A “Superload” is any load that exceeds 15 feet high, 16 feet wide, 110 feet long, and/or 120,000 pounds.” A load that fails the overload analysis also goes to an INDOT engineer, and “Loads that are reviewed by INDOT engineers require additional processing time.”

The DOR’s handbook (July 2017 edition) says superload permits over 200,000 pounds take 7 to 10 business days. Check the DOR for current timing.

Delaware

DelDOT’s OS/OW Policy and Procedures Manual (October 2015) defines a superload as a vehicle or load with any one of these: length of 120 feet or greater, width of 15 feet or greater, height of 15 feet or greater, or gross weight of 120,000 pounds or greater. It then sorts superloads into five types: length only, width only, height only, weight only, and a combination.

The manual tells you to be ready to submit a Route Survey (HP Form 16) and a SUPERLOAD Gate-Keeping Checklist (HP Form 17), and to notify the Delaware State Police at least 48 hours before the move. Review time varies by type. A superload “will not be permitted under a blanket permit.”

Virginia

Virginia’s rule, 24VAC20-82-60, covers superload single trip permits for a single move between two points that exceeds the limits for ordinary single trip permits. Each request is decided case by case, after a review or a VDOT engineering analysis, and should reach DMV at least 10 working days before the move. A move over 18 feet wide, 250,000 pounds, 200 feet long or 16 feet high may need a detailed travel plan with pull-over and layover points and written approvals from local police, utilities and VDOT.

What this means for your next move

  • Check each state’s line against your loaded dimensions. Each state on the route compares your numbers to its own threshold.
  • Add lead time. NCDOT asks for 10 business days and Virginia 10 working days. Build that into your delivery date.
  • Expect a fixed route. For an approved superload, Indiana’s handbook says “The truck configuration, dimensions, and route cannot be changed” once the engineer has analyzed them.
  • Plan for a route survey. Pennsylvania and Delaware both name a route survey form. See the route survey entry.

When a definition leaves your case open, such as height in Ohio, call that state’s permit office before you apply.