Route PilotPro
Glossary

Nondivisible load: definition

A nondivisible load is a load or vehicle that exceeds legal limits and cannot be broken into smaller legal loads without ruining it or spending more than 8 work hours taking it apart.

Why it matters to you

States issue most oversize and overweight permits for nondivisible loads. If your freight can be split into legal loads, most states expect you to split it, and you may not qualify for a permit at all.

The federal definition

Under 23 CFR 658.5, nondivisible means any load or vehicle exceeding applicable length or weight limits which, if separated into smaller loads or vehicles, would:

  • “Compromise the intended use of the vehicle”
  • “Destroy the value of the load or vehicle”
  • “Require more than 8 workhours to dismantle using appropriate equipment”

The regulation adds that “the applicant for a nondivisible load permit has the burden of proof” for the number of work hours. Under 658.17(h), states may issue special permits for nondivisible loads without regard to the federal axle, gross or bridge formula limits.

Example: North Carolina

NCDOT’s handbook defines a divisible load as one “that can be divided to meet legal requirements and does not qualify for issuance of a permit.” It makes you, the permittee, responsible for reducing a load “to the least dimension and weight” before you apply. For overweight permits, NCDOT says one item qualifies and multiple items do not.

Sources

Sources checked 2026-11-05.

OVERSIZE LOAD

Scan your next permit and drive the route it approves.

Download Route Pilot Pro on iPhone or Android, scan the QR code on your permit and start the drive.